Water district weighs a $107 million contract to replace a Cedar Creek pipeline section built more than 50 years ago

Tarrant Regional Water District staff say a break in the flood-prone section could halt operations for months; the board also votes Tuesday on doubling a borrowing program to $800 million.

Sasha Esparza· AI-assisted, edited by Jake Team

October 18, 20263 min read

Infrastructure planning - illustration, Jake Team LLC

The Tarrant Regional Water District board is set to vote Tuesday on a contract of up to $107.1 million to replace an aging stretch of its Cedar Creek pipeline, and on doubling a short-term borrowing program to $800 million to keep pace with a construction plan staff put at $2.3 billion over five years.

The board meets at 9 a.m. Oct. 20 in its board room at 800 E. Northside Drive in Fort Worth. The district's water bonds are repaid from contracts with Fort Worth, Arlington, Mansfield and the Trinity River Authority, according to the bond resolutions in the meeting packet.

A pipeline past its useful life

The contract would go to BAR Constructors for the first phase of the Cedar Creek Section 4 replacement, which runs from the Trinity River to the Cedar Creek Lake pump station.

The district's agenda memo says the existing line was built more than 50 years ago, is at the end of its useful life and has had joint failures that electromagnetic inspection tools cannot detect ahead of time. Because the route crosses flood-prone ground, a break during a long flood "could halt operations for months until waters recede and repairs can begin," the memo says.

BAR would build a new 90-inch steel pipeline alongside the old 72-inch concrete one and abandon more than eight miles of the old pipe, most of it laid in open trench with three tunnels. The larger pipe would also raise how much water the line can move.

Work at the lake pump station includes new discharge piping and flow meters, a water quality analyzer building and removal of the old chlorine and ammonia tanks.

Four firms submitted proposals. BAR's $107,110,641 price was the lowest and scored highest, 97 of 100 points, ahead of bids from McKee Utility Contractors at $113.5 million, Harper Brothers Construction at $122.3 million and SJ Louis Construction of Texas at $123.3 million. The engineer's estimate was about $129.3 million.

The scoring sheet sets substantial completion for April 30, 2029. Several related engineering, inspection and construction management contracts for the project are also on the agenda.

Borrowing as projects move

Finance Director Kathleen Ray's memo asks the board to raise the district's extendable commercial paper program for water supply from $400 million to $800 million. The program lets the district sign multiyear construction contracts without issuing bonds for the full amount up front, borrowing as cash is needed.

The memo says current commitments are about $230 million and the district expects to take on about $500 million a year in new ones over the next five years, mainly for the Integrated Pipeline, or IPL, project, the Cedar Creek pipeline replacements and the Marty Leonard Wetlands. It notes the $2.3 billion plan does not include a new water supply source.

Also on the agenda: $55 million in bonds to be sold to the Texas Water Development Board for the Mary's Creek water reclamation project, which staff estimate will save $9.3 million in interest over 30 years; a $487,441 design contract with Freese and Nichols to address seepage at Richland-Chambers Dam; and an interlocal agreement with Fort Worth dividing who builds and maintains streets, bridges, stormwater lines, canals and paseos on Panther Island.

Sources

trwd.com

trwd.com

Share

Sasha Esparza· AI-assisted, edited by Jake Team

Sasha Esparza writes about community life, schools, public safety, and local events in Fort Worth.

Related Stories

More in Texas