State filing puts the National Juneteenth Museum's construction start in March 2027 and its finish on Juneteenth 2029

The museum's registration with Texas regulators lists a 70,000-square-foot building on East Rosedale Street, an estimated $62 million cost and the City of Fort Worth as owner.

Sasha Esparza· AI-assisted, edited by Jake Team

November 20, 20262 min read

Museum construction plans - illustration, Jake Team LLC

The National Juneteenth Museum now has dates on file with the state. A project registration submitted Wednesday to the Texas Department of Licensing and Regulation lists a construction start of March 1, 2027, and a completion date of June 19, 2029, the Juneteenth holiday.

The filing, project TABS2027006134, describes the job as new construction of a museum building at 959 E. Rosedale St. in the Historic Southside. It lists:

  • Size: 70,000 square feet
  • Estimated cost: $62 million
  • Owner: City of Fort Worth
  • Design firm: KAI Design of Irving
  • Funding: the project is marked as involving public funds or public land

The tenant line names Jarred Howard. When the City Council pledged money to the museum in 2022, the city identified Howard as principal of Sable Brands and the project's developer.

The registration shows a status of "Project Registered." TDLR's project page notes that the owner of a building must get an inspection from a registered accessibility specialist no later than a year after construction is completed.

A long road to a start date

The museum has been years in planning. In September 2022, the council unanimously pledged $15 million toward what the city then described as a $70 million project, with the condition that the city pays only after the rest of the money is raised, according to a city news release at the time.

The design shown then put the museum on the second floor of a two-story building, with a restaurant, a business incubator, a 250-seat amphitheater and storefronts below, plus 55 homes in three neighboring buildings.

That release said construction could begin as early as the end of 2022 or the first quarter of 2023, with a grand opening planned for mid-2025. The new filing moves the start to 2027.

The filing does not say whether the fundraising condition attached to the city's pledge has been met, and it does not describe the other parts of the earlier plan. WFAA reported on the state filings Friday.

Sources

State of Texas

fortworthtexas.gov