Projections put data center water use between 29 billion and 161 billion gallons a year by 2030. The range is the point, and it is part of what the state's new audit is meant to settle.

Sasha Esparza

August 5, 20262 min read

Data Center Water - illustration, Jake Team LLC
Data Center Water - illustration, Jake Team LLC

Days after Texas paused new data center connections to the state grid pending an audit, the size of the gap that audit is meant to close is coming into focus.

By 2030, data centers in Texas could consume somewhere between 29 billion and 161 billion gallons of water a year. That range represents anywhere from about half a percent to nearly 3 percent of all water used in the state.

The spread is the story. A projection whose high end is more than five times its low end is not a forecast so much as a statement about how much is still unknown.

Where things stand now

Today all Texas data centers together account for less than 1 percent of state water use. Manufacturing uses about 7 percent.

The variable is cooling. A single facility using water-chilled coolant can consume up to half a billion gallons a year, while other designs use far less. Which approach a developer chooses is set at the design stage, which is why it appears on the state's audit list.

The power side

ERCOT had received requests for more than 400,000 megawatts as of April, with close to 89 percent coming from data center developers. The 248 planned projects range from 5 megawatts to 11,000 megawatts at full capacity.

Some constraints are physical rather than regulatory. Wait times for new gas turbines have reached about seven years, which limits how fast generation can be added regardless of what regulators approve.

Retail electricity prices in Texas have risen 29 percent since 2020.

Why the audit was made mandatory

The Public Utility Commission had already tried asking. Fewer than a third of 341 data centers responded to its survey, which is the specific shortfall behind the decision to make the review compulsory.

ERCOT has also moved to a batch process for reviewing clustered proposals rather than assessing each project on its own, an acknowledgment that projects in the same area compete for the same capacity.

Officials and researchers quoted on the projections include Margaret Cook of the Houston Advanced Research Center, Brian Korgel of the Energy Institute at the University of Texas at Austin, former energy regulator Alison Silverstein and ERCOT chief executive Pablo Vegas.

Sources

https://www.kut.org/energy-environment/2026-08-05/texas-data-centers-water-power-energy-use-environment

https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/

Share

Sasha Esparza

Sasha Esparza writes about community life, schools, public safety, and local events in Fort Worth.

Related Stories

More in Sport