Council calls a noon session Tuesday on taking state flood money for the Lebow Channel rebuild

The special called meeting comes ahead of the 2 p.m. work session. The state approved $90 million for the north Fort Worth flood project last December, mostly as financing, with $18.75 million as a grant.

Renata Pennington· AI-assisted, edited by Jake Team

November 27, 20262 min read

Civic Flood Relief - illustration, Jake Team LLC

The Fort Worth City Council has scheduled a special called meeting for noon Tuesday, Dec. 1, in the Council Chamber at City Hall, 100 Fort Worth Trail, with a single subject: accepting a Texas Water Development Board grant for the Lebow flood mitigation project.

The city announced the session on Nov. 25 alongside the agenda for its regular 2 p.m. work session the same day. The announcement does not give a dollar figure for the grant the council will discuss.

What the state approved

The water board voted on Dec. 16, 2025, to commit $90 million to the project from the state's Flood Infrastructure Fund, according to the board's records. Most of it, $71.25 million, is financing: the board would buy that amount of city drainage utility revenue bonds. The other $18.75 million is a grant.

The board's staff estimated the city could save about $52.4 million in borrowing costs over a 30-year schedule, on top of the grant.

In June, the board extended the city's deadline to close on the commitment from June 30 to Dec. 31, 2026. A staff memo said Fort Worth was waiting on the Federal Emergency Management Agency to decide on a separate $50 million grant request, which could lower the amount the city needs from the state.

The city's Nov. 25 notice does not say whether FEMA has ruled.

The channel

Lebow Channel is a West Fork Trinity River tributary on the city's north side. The water board's project summary calls it 75 years old and undersized, with frequent flooding of the road beside it, its crossings and nearby streets, and says some homes in the area predate the federal flood insurance rules adopted in 1980.

The plan covers 7,392 feet of channel work, including excavation along 4,000 feet of the existing channel, nine roadway crossings, rebuilt culverts, stream restoration and a 40-acre detention pond. The city's project page describes the stretch as running from Long Avenue north to DeRidder, with the pond at Long Avenue, in Council District 2.

The two schedules differ slightly. The water board's December 2025 timeline listed construction starting by the end of 2027 and finishing by the end of 2032. The city's page, which lists its status as of January 2026, shows construction starting in early 2028 and wrapping up in early 2033, with design underway now.

Tuesday's meetings can be watched live on Fort Worth TV and the city's YouTube channel.

Sources

fortworthtexas.gov

State of Texas

State of Texas

fortworthtexas.gov

Share

Renata Pennington· AI-assisted, edited by Jake Team

Renata Pennington covers Fort Worth city hall, the council, and county government.